Friendship Heights Large Main Replacement

As part of DC WASA's Capital Improvement Program, existing 20-inch cast iron water mains will be replaced at various locations in northwest. These mains were installed over 75 years ago and are approaching the end of their useful service life. As a result of a failure of these mains in 2002, DC WASA evaluated their condition and determined that they had deteriorated and were in need of replacement in several locations. In addition, several mains were found to be located on private property, and will be relocated to public space.

See complete fact sheet on Friendship Heights large main replacement (PDF 843 kb) .

Project Will Include

Installation of 20-inch and smaller ductile iron water mains. Major work items include, but are not limited to:

  • Installation of 2,050 linear feet of 20-inch diameter water main
  • Installation of 165 linear feet of 8-inch diameter water main
  • Installation of 150 linear feet of 6-inch diameter water main
  • 1,000 square yards of Portland Cement concrete pavement
  • 7,000 square yards of asphalt surface mill and overlay

Project Schedule

Start Date
June 23, 2009
Estimated Completion Date
Spring 2010
Normal work hours
7:00 a.m. to 5:00 p.m., Monday to Friday
Work requiring lane closures will only occur during non-rush hour periods
(9:30 a.m. — 3:30 p.m.)