What We Do
Anacostia Combined Sewer Separation Project, CSO 006
The Anacostia Combined Sewer Separation Project - CSO 006 was initiated in March 2008 as a component of DC WASA's overall Long Term Control Plan for reducing the overflows of the District's combined sewer system which may discharge stormwater and wastewater runoff into area waterways when it rains. This Project will involve adding new pipes that separate the flow of stormwater from wastewater and will reduce the amount of wastewater that enters the Anacostia River.
Download a more detailed Fact sheet on CSO 006 (PDF 1013 kb) .
DC WASA Work Scope Will Include
This Project encompasses the installation of water, storm and sewer pipes, providing sewer separation and lead removal, along with other DC WASA infrastructure improvements throughout the area bounded by 13th Street, Good Hope Road, Shannon Place and W Street in S.E. Washington, D.C.
Advance notification will be provided to customers directly affected by excavations required to install pipes. The final phase of the work will be restoration of the disturbed areas.
Schedule
- Contract Start Date: March 18, 2008
- Estimated Contract Completion Date: April 17, 2010
- Normal work hours will be from 7:00 A.M. to 7:00 P.M., Monday to Friday
- Work on private property shall not start before 9:00 A.M. unless other wise agreed with the property owner and/or tenant and in compliance with all other regulations.
- Work will require sidewalk closures and possibly lane closures (if necessary). Closures will only occur during non-rush periods (9:30 A.M. – 3:30 P.M.).