What We Do
Anacostia First Main Replacement
As part of DC WASA's Capital Improvement Program this project will replace the existing 12-inch and smaller diameter water mains at various locations in Ward 8, as shown in the location map in the project fact sheet (PDF 1.1 mb) . Replacement of these old, deteriorated mains will improve the water distribution system.
Download a Fact sheet on the Anacostia 1st Main Replacement project (PDF 1.1 mb) .
DC WASA Work Scope Will Include
Installation of 5,904 linear feet of 12-inch, 25,476 linear feet of 8-inch and 1,669 linear feet of 6-inch diameter water mains, gate valves, fire hydrants, water service replacements and connections, and roadway restoration.
Schedule
- Start Date
- Monday, July 7, 2008
- Estimated Completion Date
- August, 2010
- Normal work hours
- 7:00 a.m. to 5:00 p.m., Monday thru Friday/Saturday
- Work requiring lane closures will only occur during non-rush hour periods (9:30 a.m. — 3:30 p.m.)